Bonacci Infrastructure provided all major temporary works for the Clough Curtain Joint Venture as part of the Exxon Mobil PNG LNG project.
Works included the design of two new piling leaders which were fitted to a Manitowoc 16 000 crane, a cable guided ferry system across the Mubi River, barge mounted piling frames, temporary works slope stability assessments (including geogrid slope reinforcing), and an extensive peer review of a 116 metre steel truss bridge launch procedure which identified and rectified critical flaws in the structure and launch methodology.





Similar Projects
-
Gold Coast Cultural Precinct – Green Bridge
City of Gold Coast Council
-
Broken Hill Pipeline – Murray River Offtake Pump Station
John Holland Group
-
Wivenhoe Dam Upgrade
Wivenhoe Alliance